Course syllabus Z15-0088-I - Rural Roads (FZKI - WS 2019/2020)

     Information sheet          Detailed content          Timetable          ECTS syllabus          

     Slovak          English          

The units forming the course syllabus:
1.1. (allowance 0/1)
 
a.Exercise: Characteristics of agricultural services. Network of field roads. Breakdown field roads of importance and traffic intensity.

2.2. (allowance 0/3)
 
a.Exercise: Categories of field roads. Road terminology. Award of maps of the area.

3.3. (allowance 0/1)
 
a.Exercise: Design parameters of field roads. Directional elements itinerary. Proposal for a road corridor through the control line.

4.4. (allowance 0/1)
 
a.Exercise: Calculating the direction they know the route of the road - or polygon (person communication, directional arcs, medzipriamky). Width arrangement of the road. Extending the lane in the curve. Detailed structure of the situation (1:1 000).

5.5. (allowance 0/1)
 
a.Exercise: The design of the longitudinal profile under the direction of alignment of the road (M 1:1 000/100).

6.6. (allowance 0/1)
 
a.Exercise: The high-rise design elements of country roads. Design principles vertical alignment. Longitudinal gradient of vertical alignment. Skyscrapers arches. Design and calculation of the height of the polygon. Bound to give the brand profile. Completing the longitudinal profile (scale 1:1 000/100).

7.7. (allowance 0/1)
 
a.Exercise: Roadway. Transverse and superelevated road. The resulting slope. Change in cross slope of the transition line to the curve. Shoulder. Construction of the road and its proposal. Construction of flaps (M 1:100 / 100).

8.8. (allowance 0/1)
 
a.Exercise: Slopes natural body. Drainage of body travel: longitudinal drainage, cross drainage. Construction of flaps (M 1:100 / 100).

9.9. (allowance 0/1)
 
a.Exercise: Road property. Intersection. Safety devices for field trails. Brands for model cross-section. Construction of cross-sectional model (scale 1:50).

10.10. (allowance 0/1)
 
a.Exercise: Makes the detailed situation. Completing a detailed situation of the proposed field trip (scale 1:1 000).

11.11. (allowance 0/1)
 
a.Exercise: Determination of cubature earthworks proposed road (mass table). Transverse and longitudinal transport earthworks. Construction longitudinal distribution lines transport fuels (M 1:2 000)

12.12. (allowance 0/1)
 
a.Exercise: Completing the project. Technical Report. Project documentation.

13.13. (allowance 0/0)
 
a.Exercise: Presentation of the project and assessment.


Last modification made by Ing. Helena Barošková on 02/25/2019.

Type of output: